Which method should be used to evaluate mutually exclusive projects that differ in scale of production or time of completion?
Correct answer D. Net present value method
Explanation
When projects differ in size or timing, IRR rankings can conflict; NPV measures the absolute increase in wealth and so gives the correct choice.