If a project’s cash flows exceed the amount needed to repay the invested capital at its required rate of return, what will its net present value be?
Correct answer A. Positive
Explanation
NPV measures cash flows over and above recovery of capital plus its required return, so any surplus beyond that requirement makes the NPV greater than zero.