Practice mode Chemical Engineering

What does a feed-forward controller measure in order to take corrective action?

Correct answer B. The disturbance, before it affects the controlled variable

Explanation

Feed-forward measures an incoming disturbance and adjusts the manipulated variable in advance, so it can act before the controlled variable is upset. Feedback instead waits for the controlled variable to deviate. Feed-forward needs a process model and cannot correct unmeasured disturbances, so it is usually combined with feedback.