Under rule 9 of the Public Procurement Rules 2004, what were procuring agencies forbidden to do with their annual planned procurements?

Correct answer B. Split or regroup them

Explanation

Rule 9 required agencies to announce planned procurements for each financial year and proceed without any splitting or regrouping. Splitting a large purchase into small ones to stay under quotation or advertisement thresholds is a classic red flag that auditors look for in public procurement.