Under rule 13 of the Public Procurement Rules 2004, what was the minimum response time for national competitive bidding?
Correct answer D. Fifteen days
Explanation
Rule 13(1) of the 2004 Rules let procuring agencies set response times according to complexity and urgency, but never less than fifteen days for national and thirty days for international competitive bidding, measured from publication of the notice. No time limit applied in an emergency.