What is the design condition called when a high flood passes over a weir, creating high uplift pressures while the canals carry no flow?
Correct answer C. Worst condition
Explanation
Designers check weirs under the worst condition, when maximum uplift from a high flood occurs with no counteracting water load in the canals, to ensure the floor is safe.