For a given cross-sectional area and bed slope, when is a channel said to have the most economical section?
Correct answer D. All of these
Explanation
Minimising the wetted perimeter reduces friction, which maximises discharge for the given area and slope and also cuts lining and excavation costs, so all the statements apply.