If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be: May 10, 2026August 10, 2019 A.4 days B.5 days C.6 days D.7 days Show AnswerAnswer=Option A