A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work______? June 9, 2023August 10, 2019 A.23 days B.37 days C.37 D.40 days Show AnswerAnswer=Option C