A can finish a work in 7 days B in 14 days and C in 28 days. B and C start working and are forced to leave the work after 2 days. The number of days taken by A to finish the remaining work is

A.8.5 days

B.10 days

C.5.5 days

D.15.5 days

Show Answer

Answer=Option C

 